Jurupa Valley High School
Measure EE Bond Projects
Jurupa Valley High 'C' Wing Modernization
Project Approach
When embarked on this modernization project, the District seized it as an opportunity to build upon the existing Career Technical Education (CTE)programs. A re-imagined and modernized Innovation Center would promote these programs to students and their families externally, and also support the educators who are working hard to implement the PLTW curriculum and Project Based Learning at JVHS and across the District. Due to budget constraints, the District could not invest in building an entirely new structure to accommodate these programs; instead it was elected to modernize an existing, underutilized building into a higher- tech Innovation Lab that would accommodate industry equipment, integrate the latest technology, foster collaboration, and inspire students to explore and create.
Design Approach
Home to multiple STEAM (Science, Technology, Engineering, Art, Math) Pathways, the Innovation Center has been designed to promote creativity, experimentation, and a lifelong love of learning in a state-of-the-art environment, fully equipped to support Project Based Learning (PBL) and Project Lead the Way (PLTW) curriculum." - Ruhnau Clarke Architects
JVHS Innovation Center Phase I in Action!
Jaguar Stadium Modernization
About the project
The renovation was completed in two phases. Phase I consisted of new artificial turf, upgraded underground utilities, improved ADA path of travel, and new ornamental fencing. Phase II consisted of a new scoreboard, new monumental sign, additional ornamental fencing, fresh new landscape and a perforated metal screen wall. In addition, concession stands were repainted to white and blue.
Energy Efficiency (Prop 39)
Over a hundred exterior lights were removed and replaced with energy efficient LED lighting fixtures.
High Efficiency Transformers
OpTera Energy Solutions Removed and replaced 9 aging inefficient transformers at JVHS with new high energy efficiency transformers custom built to meet existing space and connectivity requirements.
The swimming pool's Variable Frequency Drive (VFD) was retrofitted to maximize energy efficiency.
The gymnasium lighting systems were retrofitted for improved energy use.
Jurupa Valley High Digital Gateway Initiative
About the project
Jurupa Unified has launched a Digital Gateway Initiative, which means that each student at Jurupa Valley High is equipped with a Chromebook to take to and from school. Each Chromebook is monitored and filtered to protect students while online. Digital Gateway is funded by short-term financing proceeds from Measure EE, the facilities bond that district voters approved in November 2014. The bond costs related to the Chromebooks will be fully paid during the life of the devices.
Digital Gateway will:
- Increase student engagement and productivity through personalized learning and equal access to technology.
- Extend and expand learning beyond the school day - anytime, anywhere learning 365 days a year, 24/7.
- Provide all students with 21st-century tools and relevant learning experiences.
- Increase 21st-century skill development in collaboration, communication, creativity, critical thinking and problem solving, digital literacy, and global awareness.
Statistics
Launched - August 2016
Jurupa Valley High Wireless Network Upgrades
About the project
Modernization of Jurupa Valley High's wired and wireless network infrastructure, replacing aging cables, and installing new wireless access points.
Wireless Network Upgrades will:
- Preserve high-speed internet access for every student in every classroom
- Ensure more stable, reliable internet service throughout the school day
- Provide internet service up to 10 times faster than the speed of the network being replace
Statistics
Completion - July 2016