Maintenance and Operations
HVAC and Auxiliary Departments
EMSISD - MAINTENANCE DEPARTMENT
JANUARY MONTLY REPORT
TEAMWORK
QUOTE OF THE MONTH
DEPARTMENT OVERVIEW
Carpentry Team- Jim Wilhite
WORK ORDERS
There are currently 3 work orders we are working on for this department.
DEPARTMENT OVERVIEW
HVAC Supervisor: Tommy Woodell
HVAC Team: Gabe Garza, Eric Lynn, George Lutes, Zac Ramos, Roger Wolfe, Flaviano Michel, David Snook
HVAC Controls : Barry Davis, Chris Mendoza
WORK ORDERS
There are currently 32 work orders we are working on for this department.
BHS HVAC HEATER PROJECT
MCMS HVAC PROJECT - DAVID AND FLAVIANO
Flaviano and David proactively worked on their units at Marine Creek Middle School before the freeze event on 1-31-23. Great job teaming up together on this and getting it addressed before the freeze!
HIGHLAND MIDDLE SCHOOL HVAC MAINTENANCE - ERIC LYNN
DEPARTMENT OVERVIEW
Fire Tech Team: Zach Page
WORK ORDERS
There are currently 9 work orders we are working on for this department.
BHS FIRE COMMUNICATION LINE PROJECT - ZACH PAGE
Zach has been working on upgrading the communication lines at all the campuses that need to be upgraded. Zach has done an awesome job teaming up with SAS and getting these campuses upgraded! Nice work this month Zach!
DEPARTMENT OVERVIEW
WORK ORDERS
There are currently 65 work orders we are working on for this department.
DEPARTMENT OVERVIEW
Mechanics Team: Jay Turner and Javier Garza
WORK ORDERS
There are currently 0 work order we are working on for this department.
PROJECT OVERVIEW
Jay and Javier will be continuing their Preventative Maintenance projects on the white fleet to make sure they stay up to date this whole year.
DEPARTMENT OVERVIEW
FREEZE - CAMPUS WALKS
The maintenance departments teamed up together and walked the campuses to make sure there was no water breaks in the campus. These teams came in the whole week of 1-30-23 and made the adjustments in areas we needed to make adjustments in to make sure the campuses stayed up and running during this freeze event! Great work on coming together across the trades and taking on this task!
TEAM ASSISTING FROM THE GROUND TO IDENTIFY WHERE A ROOF LEAK WAS LOCATED AT GES
ZACK RAMOS FIXING A UNIT THAT WENT DOWN DURING THE FREEZE AT MCMS
OPERATIONS TEAMING UP TO HANG A WHITE BOARD IN A OFFICE
DEPARTMENT OVERVIEW
Painting Team: Ben Escobal, Rodrigo Mejia
WORK ORDERS
We currently have 27 work orders to be worked on for this department.
CREEKVIEW MIDDLE SCHOOL WEIGHT ROOM PAINTING PROJECT
Ben and Rodrigo teamed up and gave the weight room at Creekview Middle School a new fresh coat of paint! They are also working with the art class at CMS and upgrading the weight room Logo! Stay Tuned !!! Nice Work Guys!
ELKINS ELEMENTARY PAINTING PROJECT
Ben and Rodrigo teamed up and gave the nurses office at Elkins Elementary School a new fresh coat of paint! They also touched up some walls in the office area!!! We have big plans for the other areas inside of Elkins during the summer! Stay Tuned!!!! Nice Work Guys!
COPPER CREEK ELEMENTARY PAINTING PROJECT
Ben and Rodrigo teamed up and gave some offices a new fresh coat of paint at Copper Creek Elementary! Nice Work Guys!
HOLLENSTEIN PAINTING PROJECT
BUILDING 5 PAINTING PROJECT
DEPARTMENT OVERVIEW
Pest Control Team: Aaron Hardisty/Double D Termite
WORK ORDERS
30 work orders were closed out for this department this month!
DEPARTMENT OVERVIEW
Roofing Team: Aaron Hardisty
WORK ORDERS
We currently have 7 work orders to be worked on for this department.
DEPARTMENT OVERVIEW
WORK ORDERS
There is currently 0 work orders we are working on for this department