MSD Construction Update
Marjory Stoneman Douglas High School
Marjory Stoneman Douglas High School’s new 30-classroom
building is on track for completion this summer.
With the MSD campus unoccupied over the past few months due to the coronavirus pandemic, construction has maintained a productive pace, ensuring the new addition will be ready for students and teachers when they return to campus for the 2020/21 school year.
Crews on site have made consistent progress since breaking ground in August 2019, and the project is on schedule to be completed in July 2020.
Once the building is ready for final inspection, only punch list work involving placement of furniture, fixtures, and equipment (FF&E) and other minor amenities will remain.
From foundation to rooftop, building a new campus addition is a process that involves careful planning, phased timelines, and consistent hard work. Click the video above to see what that process has looked like at Marjory Stoneman Douglas High School.
The temporary modular buildings, which were used to accommodate students and teachers during the construction of the new building, will be removed this summer.
Work has started to ensure the area is cleared prior to
the start of the school year, including:
The basketball courts, which had been used as the location of the temporary classrooms, will be restored once the six to eight week removal process is completed.
With all of the anticipation surrounding the new building, there may be less awareness about other upcoming renovations to existing buildings on campus, which will begin soon.
SMART PROGRAM PRIMARY RENOVATIONS
Art Room Renovation and Equipment
Building Envelope Improvements
HVAC Improvements
Fire Alarm Upgrades
Music Room Renovation
Design drawings for the campus renovations have been completed and are now pending review. Once a permit is issued, the Guaranteed Maximum Price (GMP) is expected be presented to the School Board for approval this fall, allowing contractors
to mobilize on campus.
After mobilization, construction is expected to begin by December 2020.
The School Board of Broward County, Florida, prohibits any policy or procedure which results in discrimination on the basis of age, color, disability, gender identity, gender expression, genetic information, marital status, national origin, race, religion, sex or sexual orientation. The School Board also provides equal access to the Boy Scouts and other designated youth groups. Individuals who wish to file a discrimination and/or harassment complaint may call the Director, Equal Educational Opportunities/ADA Compliance Department & District’s Equity Coordinator/Title IX at 754-321-2150 or Teletype Machine (TTY) 754-321-2158.