Heights Construction Update
A. Drywall is hung! The tapping and mudding is currently being started.
Q. What is going to happen with courtyards at Heights?
A. They will still be there. The front courtyard will continue to have plants and vegetation. The back courtyard will have cement and have shade coverings over it. This will be a great spot for students to eat lunch and work outside when it is nice.
Q. What has been completed or is near completion?
A. The structural steel improvements are nearly complete, as is the mechanical, electrical, and plumbing throughout the building. The framing in sectors 1-2 are completed.
Q. Will the breezeways look the same?
A. The breezeways will actually be enclosed. They will be enclosed by windows. Think store front windows. :)
Heights Elementary Construction Photos
New 3rd grade Classroom on 11-24
New 3rd grade Classroom on 1-12
Framing of the Breezeways
Color Board for Heights
Below is a picture of the color board (examples of carpets, flooring, paint, tile, etc.) that will be in the newly remodeled Heights Elementary School! Doesn't it look fantastic!