Building Project Community Update
Meeting Recap: May 11, 2017 & June 5, 2017
Timeline
Week Of May 1 - May 5:
All Administrative Offices and Main Office emptied and relocated
Week Of May 8 - May 12:
Conference rooms and Curriculum rooms emptied
Week Of May 15 - May 19:
Library packed
Contractors on-site
Week Of May 22 - May 26:
CST and Providers (Speech/OT/PT) offices emptied and relocated
Week Of May 30 - June 2:
Art/World Language and Teacher’s Room relocated
PTA BOGO Book Fair - (hallway outside cafeteria)
Anticipated Completion Dates:
Main Office/Administrative Offices 9/01/17
Parking Lot and Playground 9/01/17
Teacher’s Room and New Classroom 9/01/17
Heating/Ventilation/Air Conditioning 9/01/17
Handicapped Lift (Media Center-Cafeteria-Gym) 9/01/17
STEAM Lab, Tech Lab, Media Center 10/15/17
Main Entrance 12/15/17
What to Anticipate While School is in Session
- Contractors on site: Raptor screened wearing identification badges
- Impacted parking due to work vehicles on site
Main Office and Administrative Offices consolidated
Art/World Language will be in classrooms
Library packed up and closed
Computer Lab packed up and closed
Dumpsters & Porta Pot on playground
Possibility of part of the playground being fenced off
Construction to start in Library/Teacher’s Rooms, Offices, etc.
Contractors on site (badged through Raptor)
Potential parking impact
- Lack of air conditioning
- Early dismissal schedule 6/12, 6/13, 6/14, 6/15
Parent/Community Planning Opportunities
Media Center Design
STEAM Supply Donations
Parent Academy
Report Card Revisions - 2018 - 2019 School Year
Fill out the form below.