LOSD Bond Program Update
May 2019
Active Projects
Lakeridge Middle School Replacement
Bond Team for this project includes:
Tony Vandenberg, Executive Director of Project Management
Paul Eskeldson, Senior Project Manager
Jamie Harwood, Project Coordinator
Mahlum Architects – Design Team
Skanska – Construction Company
-
The contractor is excavating the site to prepare the soils for the building foundation. A large rock field was encountered under the north half of the building, causing a slight delay while the team developed a soils preparation approach for this area. This was anticipated based on earlier studies
The building permit is being reviewed by the City. The design team is responding to City questions with the goal of receiving the permit by the end of May
The Public Works permit for construction on Jean Road is nearly complete and the team expects to receive the permit by mid-June. Work on Jean Road will start upon receipt of the permit or the start of summer break, whichever is later. This will entail lane closures
Excavation at Lakeridge Junior High
Oak Creek Elementary School and Uplands Elementary School Renovations
Bond Team for this project includes:
Tony Vandenberg, Executive Director of Project Management
Paul Eskeldson, Senior Project Manager
Jamie Harwood, Project Coordinator
DOWA-IBI Group – Design Team
Triplett Wellman Contractors
Uplands:
-
The contractor is focusing on the front office area in order for the Principal and staff to move in on July 1.
Installation of the 4-classroom modular building begins
The classroom technology contractor installation begins
Oak Creek furniture and equipment will be moved into Uplands in phases as wings of the building are completed
Oak Creek:
-
The Land Use Application is in review by the City Planning Department and may be approved by the end of May
The scope of work at Oak Creek includes a complete re-cladding of the building (new siding, windows and roofing). The project will also include a secure vestibule, a new makerspace, and several interior modifications to allow for better use of space
The design team is developing plans for kitchen renovations, classroom A/V upgrades, and restroom renovations as additional scope for Oak Creek
- The Oak Creek Project is planned to be completed in the summer of 2020 and reopened for the 2020/2021 school year
Safety and Security Improvements
Bond Team for this project includes:
Tony Vandenberg, Executive Director of Project Management
David Lageson, Senior Project Manager
Jamie Harwood, Project Coordinator
Planning and Development Consultant: True North Security Consultants
Project Overview
Upgrades of safety and security features District-wide, include secure vestibules and controlled entryways, access control, security camera systems, security communications and facilities control systems, intruder locks, and improvements of exterior doors. True North Security Consultants are assisting the District with the development of security plans, programs, policies, and procedures.
- True North Security has provided a full assessment report and recommendations for safety and security projects for all facilities in the District. The consultants will work directly with the bond team and District leadership to prioritize the list of recommendations for all safety and security improvements and upgrades. During the month of June, True North will brief the District on findings and next steps for implementation
Technology Infrastructure Improvements
Bond Team for this project includes:
Tony Vandenberg, Executive Director of Project Management
David Lageson, Senior Project Manager
Jamie Harwood, Project Coordinator
James Miller, Director of Computer Network Services
Darcy Tucker, Interface Engineering: Key Consultant
Phase 2 of technology infrastructure upgrades will continue across the District during the 2018/2019 and 2019/2020 school years, including the following:
- Upgrades to all existing network cabling to high-speed CAT 6a
- Procurement of STEM/STEAM and makerspace technology equipment
- Procurement and installation of new emergency communications and classroom communications paging systems for all LOSD facilities
- Procurement of additional staff technology equipment
- Procurement and installation of select classroom media equipment
River Grove and Lake Oswego Junior High Renovations
Bond Team for this project includes:
Tony Vandenberg, Executive Director of Project Management
David Lageson, Senior Project Manager
Jamie Harwood, Project Coordinator
OH Planning + Design: Design Team
INLINE Construction – Construction Managers/General Contractor
Project Overview
Deferred maintenance renovation with architectural improvements, including safety and security, makerspace, STEM space, and seismic upgrades.
The Scope of Work at Lake Oswego Junior High includes deferred maintenance work on roofs and mechanical systems, revitalizing finishes, providing additional building security, and technology infrastructure improvements. The current building entry will be reconfigured to provide a new layer of security for students and staff. A new temporary gymnasium of approximately 8,550 square feet will serve the expanded Physical Education programs. LOSD will concurrently develop multiple areas on site including modular classrooms added north of the existing classroom wing to serve special programs, improving the softball fields, and adding a batting facility and concessions to the ball fields.
The Scope of Work at River Grove Elementary School includes revitalizing finishes, improving building security, seismic upgrades, re-roofing, deferred maintenance work, and improved program space. The current building entry will be reconfigured to provide a new layer of security for students and staff. A new modular building will be added to serve the makerspace program.
Project Activity and Scope of Work details:
- OH Planning + Design is heading up the design team for both River Grove and Lake Oswego Junior High. The Design Team is nearing completion of Construction Documents
- Bond Team is working to form a Design Advisory Team (DAT) for each school
- INLINE Construction has been selected as the Construction Manager/General Contractor and is preparing to bid the project in April/May
- Permitting is in progress. Lake Oswego Junior High permit application was turned in on April 22. OH Planning+Design currently working on return narrative to City Planning. River Grove Elementary permit application was submitted in on April 22. Geotechnical report was required to verify storm water infiltration calculations. Response from Bond Team forthcoming
Westridge Elementary School Renovation
Bond Team for this project includes:
Tony Vandenberg, Executive Director of Project Management
David Lageson, Senior Project Manager
Jamie Harwood, Project Coordinator
FFA Architecture & Design: Design Team
Mortenson Construction: Construction Manager/General Contractor
Project Overview
Lake Oswego School District (LOSD) is developing renovations to Westridge Elementary School relating to deferred maintenance, safety and security improvements, seismic remediations, accessibility improvements, plumbing code requirements, and educational programming. The existing 46,324 square feet one-story elementary school has a 4,626 square feet with attached covered play area.
-
FFA Architecture & Design is heading the Project Design Team. The Construction Document (CD) phase has been completed
Mortenson Construction is providing all Construction Manager/General Contractor services and began working with the Project Team in November. The project is fully bid out with the cost of construction fixed and in budget
The project plan is undergoing review by the City of Lake Oswego. Full construction permits are anticipated by the end of May
Construction is scheduled to commence on June 11 and complete by August 19