Learning Community Update
New Albany-Plain Local Schools 5.26.2019
Summer Brings Construction & Limited Access on Campus
Dear New Albany Families, Students, Staff & Community,
As you are aware, the passage of the 5-year permanent improvement levy in November 2017 combined with General Revenue Fund planning and grants provides the financial resources necessary to continue our work to repair, replace, and maintain capital assets throughout our school campus. We are responsible to insure our school facilities are safe, well maintained, and fully operational for our students, staff, and community.
Significant work occurs during the summer months to eliminate disruptions to the learning environment, when possible. This summer is no exception. The following information is provided to help you understand the scope of summer work scheduled that will impact our school campus.
Click here for full details on all summer construction & closures.
District-Wide
- LED Lighting Retrofit - May 31 - August 9
- Concrete Repairs - June 2 - July 31
Various sections of sidewalks and curbs will be replaced for safety; please respect cones and caution tape
Early Learning Center
- Playground Replacement - May 31 - August 1
ELC Playground CLOSED; expected to reopen Aug 2
Primary School
- Roof Replacement - May 31 - July 15
Some sidewalks and entrances may have limited access; please respect caution tape and cones Loop reconfiguration and new exit. (City of New Albany Project) - June 3 - August 2
Maintenance garage
Miller Ave is being extended to become a thru street across from the Annex. The Primary School exit and Annex parking will be relocated. Traffic may be limited at times during construction; respect the signage and flaggers.
Middle School
- Boiler Replacement - May 31 - August 9
The boiler in the MS Cafeteria building will be replaced and may require closure of sidewalk areas. - Parking Lot CLOSURE for Rose Run Construction - June 3 - August 2
Parking lot asphalt resealing during closure.
The McCoy/Middle School Lot will be CLOSED this summer to expedite Rose Run Park Construction. Staff/Visitors for the Middle School may park at any other parking lot on campus to walk to the McCoy/Middle School. Dublin-Granville Road is expected to open by mid-September. Parking lot access will reopen in August. - Cafeteria Loop and Green Spaces will be reconfigured to connect with Rose Run Park. May 31 - August 2
Loop will reopen by mid-September for express drop-off and pick-up lane and MS/HS special needs transportation services. Sidewalk areas may be limited occasionally.
High School
- Metal Roofs- May 31 - August 2
- Boiler Replacements - May 31 - August 9
- Eagle Stadium, Baseball, and Softball Scoreboards - July 1 - August 2
Easton E3 Learning Lab
- Exterior Deck (pending building permit approval et al.) Date to be determined
Tennis Courts
- Tennis court refurbishment and HS metal roof fabrication - May 31 - July 31
McCoy Center for the Arts
- Exterior Painting - June 3 - August 2
As illustrated, there are numerous capital projects that will occur this summer in addition to the routine maintenance and cleaning. We thank you in advance for your patience and cooperation to ensure everyone’s safety. Additional information will be shared should timelines change for any unforeseen circumstances, including weather delays.
Please respect posted signage, cones, and caution tape as our contractors and staff work diligently to repair, replace, and maintain our incredible school campus before the first day of school for students in grades 1-12 on Thursday, August 15, 2019.
Best,
Michael Sawyers
Superintendent
New Albany- Plain Local Schools