Construction update
The excitement is building at Mounds View
Road Work and Construction Update
The rain has created a number of issues with the ongoing work on Lake Valentine Road. The contractor, MUE, will be working the remainder of the week and Saturday, if needed, to prepare for bituminous (blacktop) on Monday.
The schedule will be as follows:
Wednesday - Change lane closure, traffic will be moved to the north side of the road.
Thursday - Storm lines will be set.
Friday - Crane is scheduled to set structure. Final connections will be made and the road will be backfilled.
Saturday - Any unfinished work will be completed.
Monday - Traffic controls will be removed and road will be patched after school.