Rancho Elementary School
RES Modernization/Construction Update
February 27, 2020
Modernization Project Status
We are excited to share that the modernization project at Rancho Elementary School is progressing as planned. We have moved beyond demolition and foundation preparation. Currently, new slabs are being poured, and structures are being erected. Though there are labor and supply challenges industry-wide due to COVID-19, we have been fortunate to date on the Rancho project and have not encountered any issues that would prevent the site from opening for fall 2021, as scheduled.
The next update will be shared before Spring break, consistent with the timelines shared below.
Next Steps for RES Families
RES attendance area families will receive communication the week of March 8-12 to confirm their return to RES for the 2021/22 school year. Families will have the opportunity to participate in a special transfer window to submit requests to remain at their currently assigned school site. All transfer requests are based on space availability.
Enrollment is also currently open for new students. Please visit our enrollment website to enroll new RES students.
RES Staff Information
Certificated Employees:
The staffing process will follow the approved Memorandum of Understanding (MOU). All RES certificated staff has the first right of refusal for return. Human Resources will be communicating with RES certificated staff regarding timelines and processes before Spring break. The goal is to provide assignments by mid/April, early May.
Teacher moving days: The RES campus will not be accessible to staff until late July, based on the current construction timeline. We will provide more information regarding logistics and timelines in future communication. All packing and moving of materials will be coordinated between M&O, Purchasing, and Human Resources and will be consistent with the MOU.
Classified Employees:
The staffing process will follow the approved Memorandum of Understanding (MOU). All RES classified staff has the first right of refusal for return. Human Resources will be communicating with RES classified staff regarding timelines and processes in early May.
Computers, Tech, Materials:
The Offices of Information Management and Accountability and Assessment are currently tracking where RES computers were sent and working through the logistics to ensure the RES campus has the necessary tech.
Latest Photos of Renovation Work
New Classroom and Library Building
Old Library to Classrooms
Administration Office
New Kinder Restroom Building
Temecula Valley Unified School District
RES Renovation Project Website
https://ca02208611.schoolwires.net/RESrenovationproject
Email: lboss@tvusd.us