Bond Update
March 2023
Audubon Elementary

During the March board meeting, PBK Architects presented the renderings of the new Audubon Elementary School. You can download the complete presentation below.
Audubon Elementary animation
Board Approves Guaranteed Maximum Price for Elementary
The Board approved $33,514,542 for the construction of the new Audubon Elementary. This price is $1 million under budget.
The construction will include the following:
- increased flex space for students,
- durable, low-maintenance flooring,
- and enhanced safety and security that exceeds the state requirements.
The construction timeline is on track to meet the August 2024 opening. Meeting this timeline required ordering electrical switchgear in January, as the lead time is 52 weeks.
Magnolia ISD