Construction update
Construction continues at a rapid pace
Edgewood’s construction continues at a rapid pace
Edgewood’s construction continues at a rapid pace this spring and is ahead of schedule. The entire project was scheduled for completion in December, but now the project is scheduled to be complete by September. A few recent updates:
- The south six-classroom addition is complete.
- Furniture arrived over spring break.
- The science room will be complete this week.
- Cafeteria renovation has started.
Watch this brief video to get a 360-degree interior view of the project captured last month.
Watch this time-lapse look at gym construction captured over seven weeks in February and March.
Edgewood's gym construction timelapse